EPR Go Live

Go No Go Criteria Template

This template provides a checklist to review for your EPR Go Live. This list is NOT exhaustive and will need to be adjusted depending on your EPR Provider, your EPR Programme Organization and your EPR Programme Scope.

Your Guide To EPR Go Live Go No Go

What’s Inside:

  • Common Criteria by Workstream: The list of Workstreams will depend on your EPR Programme Scope and Organization. If you are doing a EPR Upgrade or full EPR Implementation, if you include Labs Modules or Pharmacy Modules or keep them separated, it won’t be the same.
  • Who own the criteria in the organization placeholder: The owner role could change depending on your Programme Organization
  • Due Date Values Placeholder: Due Dates are general recommendations. To secure the GO LIVE – We recommend to start setting Gate Review up to 5 to 6 weeks before Go Live and the Final Go No Go Meeting not later than 1 week before Go Live.
Rag
Green On track for completion by due date
Amber At risk of missing due date; will not slip more than 1 week vs. target
Red Not achievable by due date. Urgent action is required to recover.
Blue Complete
GNG Ref Workstreams Go No Go Criteria Description Owner Role
GNG1 Abstracting Build Completed and Signed Off Workstream Lead
GNG2 Abstracting All P1 issues closed Workstream Lead
GNG3 Abstracting Abstracting Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG5 Clinical Safety All Critical Criteria Completed and Signed Off Clinical Safety Officer
GNG6 Clinical Safety All Hazard log documents Completed and Signed Off by all parties Clinical Safety Officer
GNG7 Clinical Safety All SOPs Completed and Signed Off Clinical Safety Officer
GNG9 Data Migration Final trial load completed successfully and has all entry and exit criteria met Data Migration Lead
GNG10 Data Migration All DM P1 issues closed Data Migration Lead
GNG11 Data Migration Data Reconciliation Process Defined and Signed Off Data Migration Lead
GNG12 Data Migration Data Validation Process and Ownership Agreed and Documented Data Migration Lead
GNG13 Data Migration Data Migration Cutover Detailed Plan Defined and Signed Off Data Migration Lead
GNG15 EPR Provider Technical Build Completed and Signed Off EPR Project Manager
GNG16 EPR Provider Technical Dress Rehearsal completed and timings/procedures been adjusted accordingly in the Go Live Plan EPR Project Manager
GNG17 EPR Provider EPR Technical Cutover Detailed Plan Defined and Signed Off EPR Project Manager
GNG18 EPR Provider EPR Provider Project Team Resource Rota Agreed and Validated EPR Project Manager
GNG19 EPR Provider EPR Provider Support Team Resourced and Scheduled for GO LIVE EPR Project Manager
GNG21 Infrastructure All hardware tested and deployed Workstream Lead
GNG22 Infrastructure End-to-end IT Service Model documented Workstream Lead
GNG23 Infrastructure Recovery Point for Rollback tested and Process Signed Off Workstream Lead
GNG24 Infrastructure Infra Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG25 Infrastructure Infra Cutover Resources Plan for Go Live Agreed and Validated Workstream Lead
GNG27 Interfaces All 3rd Party Interfaces tested and signed off Workstream Lead
GNG28 Interfaces All EPR Interfaces tested and signed off Workstream Lead
GNG29 Interfaces All P1 issues closed Workstream Lead
GNG30 Interfaces Interface Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG31 Interfaces Interface Cutover Resources Plan for Go Live Agreed and Validated Workstream Lead
GNG33 Labs All P1 issues closed Workstream Lead
GNG34 Labs Cellular Pathology Testesd and Signed Off Workstream Lead
GNG35 Labs Cellular Pathology SOP Signed Off Workstream Lead
GNG36 Labs Blood Transfusion Testesd and Signed Off Workstream Lead
GNG37 Labs Blood Transfusion SOP Signed Off Workstream Lead
GNG38 Labs Blood Science / Specimen Reception Testesd and Signed Off Workstream Lead
GNG39 Labs Blood Science / Specimen Reception SOP Signed Off Workstream Lead
GNG40 Labs Microbiology / Bacteriology Testesd and Signed Off Workstream Lead
GNG41 Labs Microbiology / Bacteriology SOP Signed Off Workstream Lead
GNG42 Labs Virology/Immunology Testesd and Signed Off Workstream Lead
GNG43 Labs Virology/Immunology SOP Signed Off Workstream Lead
GNG44 Labs Labs Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG45 Labs Labs Operational & IT Resources Plan for Go Live Agreed and Validated Workstream Lead
GNG47 Nursing Build Completed and Signed Off Workstream Lead
GNG48 Nursing All P1 issues closed Workstream Lead
GNG50 Pharmacy EPMA Build Completed and Signed Off Workstream Lead
GNG51 Pharmacy Testing by Pharmacists Completed and Signed Off Workstream Lead
GNG52 Pharmacy All P1 issues closed Workstream Lead
GNG53 Pharmacy Discharge letter & Outpatients Letter Build Signed Off Workstream Lead
GNG54 Pharmacy Downtime Procedures Signed Off Workstream Lead
GNG55 Pharmacy Prescriptions Data Catch Up Process Agreed and Rehearsed Workstream Lead
GNG56 Pharmacy Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG57 Pharmacy Pharmacy Ops and IT Resource Plan for Go Live Agreed and Validated Workstream Lead
GNG59 Radiology Build Completed and Signed Off Workstream Lead
GNG60 Radiology Radiology Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG61 Radiology Radiology Ops and IT Resource Plan for Go Live Agreed and Validated Workstream Lead
GNG63 RBAC All RBAC Issues closed or with mitigation in place before Go Live Change Manager
GNG64 RBAC All Staff have access to the system and have tested that their access level matches with their role Change Manager
GNG65 RBAC RBAC Go Live Support defined & agreed with all parties Change Manager
GNG66 RBAC Service Desk Level 2 Trained on RBAC Change Manager
GNG68 Reporting All P1 issues closed Workstream Lead
GNG69 Reporting Reporting available at Go Live agreed and signed off Workstream Lead
GNG70 Reporting Reporting available Post Go live agreed and signed off Workstream Lead
GNG71 Reporting Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG72 Reporting Cutover Resources Plan for Go Live agreed Workstream Lead
GNG74 Theatres Build Completed and Signed Off Workstream Lead
GNG75 Theatres All P1 issues closed Workstream Lead
GNG76 Theatres Theatre Cutover Detailed Plan Defined and Signed Off Workstream Lead
GNG77 Theatres Theatre Ops Resource Plan for Go Live Agreed and Validated Workstream Lead
GNG79 Change Divisional Communication Plan Agreed Change Manager
GNG80 Change Divisional Communications Drafted and Validated Change Manager
GNG81 Change Divisional Communications Sent to All Users Change Manager
GNG83 Training 80-90% of staff trained completed Change Manager
GNG84 Training All staff aware of any current system limitations and their workarounds Change Manager
GNG85 Training End User competency targets are achieved, or mitigation plans in place for those not meeting the targets Change Manager
GNG86 Training Floorwalkers trained and ready Change Manager
GNG87 Training EPR Champions trained and ready Change Manager
GNG88 Training Super Users Trained and ready Change Manager
GNG90 Programme All UAT Completed & Signed Off Programme Manager
GNG91 Programme All Issues & Risks been addressed and agreed upon with the Programme Board Programme Manager
GNG92 Programme Floorwalkers HIred and Rotas Completed Programme Manager
GNG94 Cutover Data Migration Dress Rehearsal completed and timings/procedures been adjusted accordingly in the Go Live Plan Cutover Manager
GNG95 Cutover Downtime Dress Rehearsal completed and timings/procedures been adjusted accordingly in the Go Live Plan Cutover Manager
GNG96 Cutover Data Catch Up Dress Rehearsal completed and timings/procedures been adjusted accordingly in the Go Live Plan Cutover Manager
GNG97 Cutover Full Technical and Operational Dress Rehearsal completed and timings/procedures been adjusted accordingly in the Go Live Plan Cutover Manager
GNG98 Cutover Go Live Approach Signed Off by the Programme Board Cutover Manager
GNG99 Cutover Overall Cutover Detailed Plan Defined and Signed Off Cutover Manager
GNG100 Cutover Rollback Approach Defined and Agreed Cutover Manager
GNG101 Cutover Rollback Criteria Listed and Agreed Cutover Manager
GNG102 Cutover Rollback Detailed Plan Defined and Agreed Cutover Manager
GNG103 Cutover Cutover Resource Rotas Completed and Validated for Cutover Weekend Cutover Manager
GNG104 Cutover EPR Support Team engaged and resourced for Go Live & ELS Cutover Manager
GNG105 Cutover Command & Control Centre available, resourced and documentation ready Cutover Manager
GNG106 Cutover Command & Control Centre Decision Points Agreed Cutover Manager
GNG107 Cutover Service Desk Level 1 engaged, resourced, and documented for Go Live & ELS (early life Support) Cutover Manager
GNG108 Cutover Early Life Support Model and Duration Agreed Cutover Manager
GNG109 Cutover Early Life Support (ELS) Exist Criteria List Agreed Cutover Manager
GNG110 Cutover BAU Support Model Agreed and Signed Off Cutover Manager

 

Download The Document Now

Get Started

Start A New Cutover Today

Embarking on a cutover is a transformative journey. Our mission is to make this journey as smooth and enjoyable as possible. With our expert guidance and tailored approach, a successful go-live is within reach for anyone.

Book your call today or drop a message on our contact form to start your journey to seamless transitions!

Team Work makes the dream works